Wanted to touch base on some items that Matthias brought up about release dates and that our roadmap is out of date.

Typically our CR & Final releases are shorter release cycles because at that point its functionality complete, and working on demos, docs, and bugs.  Also moving to just times in the month instead of dates is a better idea imo.

So I would say:

1.0.0.M6 => late October 2012
1.0.0.M7 => late December 2012 (before the holidays!)
1.0.0.CR1 => mid January 2013 (roughly 2-3 weeks after M7)
  - All libraries and primary demo's should be functionally complete before CR1.
1.0.0.CR2/Final => early February 2013 (2-3 weeks after CR1)
1.0.0.Final => late February 2013 (only if required)

Thoughts?

-Jay


_______________________________________________
aerogear-dev mailing list
[hidden email]
https://lists.jboss.org/mailman/listinfo/aerogear-dev
qmx
Reply | Threaded
Open this post in threaded view
|

Re: [aerogear-dev] 1.0.0.Final release dates and AEROGEAR-521

qmx
Administrator
Looks awesome overall, and the buffer time between M6 & M7 helps a lot :)

On Oct 22, 2012, at 10:41 AM, Jay Balunas wrote:

> Hi All,
>
> Wanted to touch base on some items that Matthias brought up about release dates and that our roadmap is out of date.
>
> Typically our CR & Final releases are shorter release cycles because at that point its functionality complete, and working on demos, docs, and bugs.  Also moving to just times in the month instead of dates is a better idea imo.
>
> So I would say:
>
> 1.0.0.M6 => late October 2012
> 1.0.0.M7 => late December 2012 (before the holidays!)
> 1.0.0.CR1 => mid January 2013 (roughly 2-3 weeks after M7)
>  - All libraries and primary demo's should be functionally complete before CR1.
> 1.0.0.CR2/Final => early February 2013 (2-3 weeks after CR1)
> 1.0.0.Final => late February 2013 (only if required)
>
> Thoughts?
>
> -Jay
>
>
> _______________________________________________
> aerogear-dev mailing list
> [hidden email]
> https://lists.jboss.org/mailman/listinfo/aerogear-dev

-- qmx


_______________________________________________
aerogear-dev mailing list
[hidden email]
https://lists.jboss.org/mailman/listinfo/aerogear-dev
Reply | Threaded
Open this post in threaded view
|

Re: [aerogear-dev] 1.0.0.Final release dates and AEROGEAR-521

Bruno Oliveira
In reply to this post by Jay Balunas
+1


-- 
"The measure of a man is what he does with power" - Plato
-
@abstractj
-
Volenti Nihil Difficile

On Monday, October 22, 2012 at 10:41 AM, Jay Balunas wrote:

Hi All,

Wanted to touch base on some items that Matthias brought up about release dates and that our roadmap is out of date.

Typically our CR & Final releases are shorter release cycles because at that point its functionality complete, and working on demos, docs, and bugs. Also moving to just times in the month instead of dates is a better idea imo.

So I would say:

1.0.0.M6 => late October 2012
1.0.0.M7 => late December 2012 (before the holidays!)
1.0.0.CR1 => mid January 2013 (roughly 2-3 weeks after M7)
- All libraries and primary demo's should be functionally complete before CR1.
1.0.0.CR2/Final => early February 2013 (2-3 weeks after CR1)
1.0.0.Final => late February 2013 (only if required)

Thoughts?

-Jay


_______________________________________________
aerogear-dev mailing list


_______________________________________________
aerogear-dev mailing list
[hidden email]
https://lists.jboss.org/mailman/listinfo/aerogear-dev
Reply | Threaded
Open this post in threaded view
|

Re: [aerogear-dev] 1.0.0.Final release dates and AEROGEAR-521

Matthias Wessendorf
+1

updated https://issues.jboss.org/browse/AEROGEAR-521

-M


On Mon, Oct 22, 2012 at 3:16 PM, Bruno Oliveira <[hidden email]> wrote:

> +1
>
>
> --
> "The measure of a man is what he does with power" - Plato
> -
> @abstractj
> -
> Volenti Nihil Difficile
>
> On Monday, October 22, 2012 at 10:41 AM, Jay Balunas wrote:
>
> Hi All,
>
> Wanted to touch base on some items that Matthias brought up about release
> dates and that our roadmap is out of date.
>
> Typically our CR & Final releases are shorter release cycles because at that
> point its functionality complete, and working on demos, docs, and bugs. Also
> moving to just times in the month instead of dates is a better idea imo.
>
> So I would say:
>
> 1.0.0.M6 => late October 2012
> 1.0.0.M7 => late December 2012 (before the holidays!)
> 1.0.0.CR1 => mid January 2013 (roughly 2-3 weeks after M7)
> - All libraries and primary demo's should be functionally complete before
> CR1.
> 1.0.0.CR2/Final => early February 2013 (2-3 weeks after CR1)
> 1.0.0.Final => late February 2013 (only if required)
>
> Thoughts?
>
> -Jay
>
>
> _______________________________________________
> aerogear-dev mailing list
> [hidden email]
> https://lists.jboss.org/mailman/listinfo/aerogear-dev
>
>
>
> _______________________________________________
> aerogear-dev mailing list
> [hidden email]
> https://lists.jboss.org/mailman/listinfo/aerogear-dev
>



--
Matthias Wessendorf

blog: http://matthiaswessendorf.wordpress.com/
sessions: http://www.slideshare.net/mwessendorf
twitter: http://twitter.com/mwessendorf
_______________________________________________
aerogear-dev mailing list
[hidden email]
https://lists.jboss.org/mailman/listinfo/aerogear-dev